What are the criteria for a project for Maiden Supply?

Posted on

Time: Most of our projects are made in Asia, so a few things usually come into play. First is lead-time: a typical new custom order may take from 10-14 weeks to develop, sample, manufacture, ship and deliver. The more front-end development and sampling there is, the longer of course. Reruns can be much quicker, like 8-10 weeks. And rush jobs including air shipments can be as low as 4-6 weeks.

Quantity: Most clients think an order from Asia needs to be in large quantities, but that is not always true. Depending on the complexity and materials involved we do many jobs as low as 250 or 500 pcs. We do larger jobs in quantities up to millions as well.